"

Building Design Cost Management

Chapter 1 | Chapter 2 | Chapter 3 | Chapter 4 | Chapter 5 | Chapter 6 | Chapter 7 | Chapter 8 | Chapter 9 | Chapter 10 | Chapter 11 | Chapter 12
Approach | BCIS Information | Case Study Design Information
Powerpoint slides
Andy Ross | Dave Jaggar | Jim Smith | Peter Love
Quantity Surveying | Construction Management | Architecture | Civil Engineering | Construction I.T.
Building Organisations- Carillion plc | Building Organisations - McCarthy and Stone | Architects | Engineers - Betchel
subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link | subglobal7 link
subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link | subglobal8 link

Picture of the textbook associated with the site


Building Design Cost Management

Case Study - BCIS Information - Available Information - Cost

 

Electronics factory C A - 1 ( 2 ) - 4,790
Building Function : 275.5 - Factories for electronics, computers, or the like
Type of Work : New build
Gross Floor Area : 4,790 m2
Job Title : Electronics Factory, Belfast
Location : Belfast, Northern Ireland
District : Belfast
Grid Reference :  
Dates : Receipt : 17-May-1996
  Base : 17-May-1996
Project Details : Single storey steel framed electronics factory with integral 2 storey office and plant accommodation together with external works including precast concrete and macadam paving, brick and precast concrete crib wall, metal fences, landscaping, services, drainage and security hut.
Site Conditions : Poor ground conditions with contaminated soils requiring cut and fill. Demolition of existing factory. Unrestricted working space and site access.
Market Conditions : Project tender price index: 80 on 1985 BCIS Index Base
Client :  
Tender Documentation : Bill of Quantities
Selection of Contractor : Selected competition
No of Tenders : Issued : 6    Received : 6
Contract : GC/Wks/1 edition 2
Contract Period ( mths ) : Stipulated : 5  Offered : -  Agreed : 5
Cost Fluctuations : Fixed
Tender Amended : PC/Provisional Sums revised
Tender List : £ 3,157,800 -  
  £ 3,196,403 1.2%  
  £ 3,240,000 2.6%  
  £ 3,394,012 7.5%  
  £ 3,419,985 8.3%  
  £ 3,468,952 9.9%  
Contract Breakdown :     
Measured Work £ 1,021,206   
Provisional Sums £ 58,500   
Prime Cost Sums £ 1,691,368   
Preliminaries £ 59,594   
Contingencies £ 43,500   
Contract Sum £ 2,874,168   
Accomodation and Design Features : Electronics factory with integral offices. PCC piles, concrete pad, ground beams and slab, PCC upper floor and entrance canopy. Steel frame and stairs. Block walls. Cladding to flat steel roof and walls. Aluminium windows and roller shutters. Block and proprietary partitions. Flush doors. Plasterboard to walls and ceilings; vinyl, carpet and raised access floors. Fittings. Sanitaryware. M&E services by nominated sub-contractor. External works with Tarmac and PCC paving, PCC and brick walls, metal fences, landscaping, service, drainage, security hut.
Basement 0 m2 Area of External Walls 2,150 m2   
Ground Floor 4,160 m2 Wall to Floor Ratio 0.45% %  
Upper Floors 630 m2 Average Storey Heights

Basement - m   
Gross Floor Area 4,790 m2 Ground - m   

Upper - m   
Usable Area 3,800 m2
Circulation Area 200 m2 Internal Cube - m3   
Ancillary Area 738 m2
Internal Divisions 52 m2 Spaces Not Enclosed - m2   

Gross Floor Area 4,790 m2 Number of Units 1    

Functional Unit Rate
3800 - m2 usable floor area £ 653
 
Storeys as % of Gross Floor Area:
single storey 73.70%
2 storeys 26.30%

 

Analysis
Element  Total Cost   Cost per
 m2 
 Element Unit
Quantity 
 Element Unit
Rate 
 Percent-
 age 
1 Substructure £ 227,143  £ 47.42        7 %   
2A Frame £ 274,031  £ 57.21        9 %   
2B Upper floors £ 10,681  £ 2.23       
2C Roof £ 163,635  £ 34.16        5 %   
2D Stairs £ 25,519  £ 5.33       
2E External walls £ 411,919  £ 86.00        14 %   
2F Windows and external doors £ 91,586  £ 19.12        3 %   
2G Internal walls and partitions £ 92,409  £ 19.29        3 %   
2H Internal doors £ 68,823  £ 14.37        2 %   
2 Superstructure £ 1,138,603  £ 237.70        39 %   
3A Wall finishes £ 18,707  £ 3.91       
3B Floor finishes £ 106,509  £ 22.24        3 %   
3C Ceiling finishes £ 31,360  £ 6.55        1 %   
3 Internal finishes £ 156,576  £ 32.69        5 %   
4 Fittings £ 13,494  £ 2.82       
5A Sanitary appliances Included in element 5F
5B Services equipment          
5C Disposal installations Included in element 5F
5D Water installations Included in element 5F
5E Heat source          
5F Space heating and air treatment (includes others) £ 484,226  £ 101.09        16 %   
5G Ventilating systems Included in element 5F
5H Electrical installations (includes others) £ 393,938  £ 82.24        13 %   
5I Gas installations          
5J Lift and conveyor installations          
5K Protective installations Included in element 5H
5L Communications installations Included in element 5H
5M Special installations Included in element 5F
5N Builder's work in connection £ 13,684  £ 2.86       
5O Builder's profit and attendance          
5 Services £ 891,848  £ 186.19        31 %   
 Building sub-total £ 2,427,664  £ 506.82        84 %   
6A Site works £ 288,366  £ 60.20        10 %   
6B Drainage £ 25,824  £ 5.39       
6C External services £ 9,220  £ 1.92       
6D Minor building works £ 20,000  £ 4.18       
6 External works £ 343,410  £ 71.69        11 %   
7 Preliminaries £ 59,594  £ 12.44        2 %   
 Total (less Contingencies) £ 2,830,668  £ 590.95        98 %   
8 Contingencies £ 43,500  £ 9.08        1 %   
 Contract sum £ 2,874,168  £ 600.04        100 %   

 

Specification
Element Specification
1 Substructure C35/20mm reinforced concrete bed 250mm, power floated; precast driven piles with insitu pad and ground beams.
2A Frame Single portal steel frame, centrally supported by a line of columns.
2B Upper floors Contractor designed precast concrete upper floors, 280mm thick.
2C Roof Composite insulated panels, Kingspan to flat steel roof. Asphalt roofing to BS988, 20mm thick including sheeting felt and chippings in hot bitumen. Aluminium rain water goods.
2D Stairs Straight internal steel stairs, metal spiral external staircase.
2E External walls Hollow concrete block external walls in gauge mortar ne 5N/mm2, 215mm thick. Smooth flat aluminium insulated sheet cladding on steel frame.
2F Windows and external doors Windows and doors by nominated sub-contractor. Vertical steel shutters.
2G Internal walls and partitions 100 and 215mm concrete facing blockwork and proprietary partitions; WC cubicles.
2H Internal doors Half hour fire flush doors, folding partitions, roller shutter doors.
3A Wall finishes 2 coats plaster and plasterboard, vinyl wallpaper. Emulsion paint.
3B Floor finishes Sand and cement (1:3) screed, 60mm thick; mastic asphalt paint. Vinyl static control sheeting and tiles; carpet tiles. Raised access floor.
3C Ceiling finishes Plasterboard. Armstrong Minaboard suspended ceilings; some Minatone to steelwork.
4 Fittings Kitchen fittings, signs, handrails, mirrors etc.
5A Sanitary appliances Sanitary fittings, soil and waste pipes. Costs included in 5F.
5F Space heating and air treatment PC sum for low pressure hot water heating, oil storage unit, ventilation, sanitaryware, disposal, hot and cold water.
5H Electrical installations PC sum for electrical power and light, sub-mains, main switchgear.
5L Communications installations Fire alarm, CCTV security system, telephones.
5M Special installations Compressed air, nitrogen installation. Cost in 5F.
5N Builder's work in connection Holes and chases for electrical and mechanical services.
6A Site works Demolitions. Precast concrete and macadam roads and parking (£136759), brick and precast concrete paths and pavings (£2289); concrete crib retaining walls (£18485); galvanised steel palisade fencing (£6469); landscaping (£104564).
6B Drainage Concrete pipes for storm and foul drainage including manholes.
6C External services Incoming electricity, water and telephone mains.
6D Minor building works Security hut £20000.
7 Preliminaries 2.15% of remainder of Contract Sum (excluding Contingencies).
8 Contingencies 1.57% of remainder of Contract Sum (excluding Preliminaries).

 

Credits

 Submitted by:

Home

Building Design Cost Management Associates,

 

 

Website Development Partners

BCIS
BCIS online
Royal Institute of Chartered Surveyors
University of Melbourne
Edith Cowan University