| Element |
Specification |
| 1 |
Substructure |
Excavation in unstable ground. 1995m2 Type 3 crushed rock. Concrete
C35/20 in foundation trenches, C40/20 reinforced concrete slab, power
float finish, 200mm thick. Reinforced concrete stanchion bases. 215mm
precast concrete block walling. |
| 2A |
Frame |
PC sum £122000 for single span steel portal frame. |
| 2C |
Roof |
BSC Colorcoat steel cladding, insulated core and powder coated inner
skin. Translucent rooflights. Kingspan Highline steel gutters. PVC
rainwater pipes. |
| 2E |
External walls |
Precast concrete block dwarf walls, rendered, with BSC Colorcoat
insulated composite metal cladding. |
| 2F |
Windows and external doors |
Kawneer 102 series double glazed aluminium windows and external
screens; Leaderflush doors. 2No electrically operated steel roller
shutters. |
| 2G |
Internal walls and partitions |
10.5N/mm2 precast fairfaced concrete blocks, mainly 215mm. Toilet
cubicles. |
| 2H |
Internal doors |
51No 44mm Leaderflush solid core doors in softwood frames. |
| 3A |
Wall finishes |
2 coats Carlite plaster and vinyl emulsion to blockwork. |
| 3B |
Floor finishes |
Sealed concrete floor with 2mm Larcote SL or Laybon Sealdeck; 421m2
vinyl flooring; 86m2 ceramic tiles; 261m2 Interface Genesis carpet. |
| 3C |
Ceiling finishes |
1122m2 Armstrong Minaboard Dune suspended ceilings. |
| 4 |
Fittings |
Minor shelving, vanity kitchen units, bench seats, reception desk.
|
| 5A |
Sanitary appliances |
14No WCs, 15No wash basins, included in 5F. |
| 5C |
Disposal installations |
Included in 5F. |
| 5D |
Water installations |
Included in 5F. |
| 5E |
Heat source |
Included in 5F. |
| 5F |
Space heating and air treatment |
PC sum £174000 for 2 boilers, calorifiers, compressors, dryer, air
receiver, 2 toilet extract fans, 2 general extract fans, 7 smoke
ventilators. |
| 5G |
Ventilating systems |
Included in 5F. |
| 5H |
Electrical installations |
PC sum £150000 for electric light, power, switchgear and CCTV. |
| 5K |
Protective installations |
PC sum £52200 for sprinklers. |
| 5L |
Communications installations |
Intruder alarm and fire detection. |
| 5N |
Builder's work in connection |
Concrete bases, tank platforms, holes, pipe casings. |
| 6A |
Site works |
Grassing; 4462m2 reinforced concrete roads; 4057m2 asphalt roads;
1801m2 macadam paving; 2022m2 macadam footpaths; chain link fencing,
rendered block retaining wall with galvanised balustrading. |
| 6B |
Drainage |
2915m2 PVC drain pipes, 110mm diameter; 92No gullies; 44No manholes.
Pumping chamber. |
| 6C |
External services |
Oil supply, sprinkler mains, water, electricity. |
| 6D |
Minor building works |
Security hut, utility building and chemical store with rendered block
walls and composite roof panels. |
| 7 |
Preliminaries |
8.04% of remainder of Contract Sum (excluding Contingencies). |
| 8 |
Contingencies |
2.44% of remainder of Contract Sum (excluding Preliminaries).
|